Three Phase Power Calculation: Requirements Step by Step
A three-phase power calculation starts with a per-phase load schedule. Convert every load to kVA, apply demand factors, balance single-phase loads across L1, L2, and L3, check power factor and motor starting, and add a growth margin. The core formula is kVA = (√3 × V × I) ÷ 1,000, where V is line-to-line voltage and I is line current. That’s the whole method in one paragraph.
The formula is the easy part. The expensive mistakes happen before it.
This opening example is an illustrative composite. A fabrication shop totaled 180 kW of nameplate load, assumed a power factor of 1, and ordered a 180 kVA set. The full calculation landed at 228 kVA once power factor, a single-phase welder, and a 15% growth allowance were included. The set was 21% undersized before the compressor started.
We build diesel and gas generator sets from 8 kVA to 4,000 kVA. In our experience, the load schedule decides whether a quotation is right long before brand or price enters the conversation.
This guide gives you the formulas, a six-step schedule, a full 480 V example, and the errors that move the answer most. If you already have a load list, send it to our engineering team for a review before you specify equipment.
Key Takeaways
– Three phase power calculation starts with a per-phase load schedule, not a single formula. The formula sizes the circuit; the schedule defines the requirement.
– Connected load is not demand load. Demand and diversity factors often cut the requirement by 20% to 40%, while power factor and motor starting push it back up.
– Use line-to-line voltage with √3 and line-to-neutral voltage with 3. Mixing them understates the answer by 42% or overstates it by 73%.
– Balance single-phase loads across L1, L2, and L3 before you total the panel. A balanced total can still hide an overloaded phase.
– State the result as total kVA, kW at a stated power factor, maximum per-phase current, voltage, frequency, and starting duty.
Three-Phase Power Calculation: The Formulas You Need

For a balanced three-phase load, real power is P = √3 × V_LL × I_L × PF. Apparent power is S = √3 × V_LL × I_L. If you have line-to-neutral voltage, replace √3 × V_LL with 3 × V_LN.
| Quantity | With line-to-line voltage | With line-to-neutral voltage |
|---|---|---|
| Real power, P (W) | √3 × V_LL × I_L × PF | 3 × V_LN × I_L × PF |
| Apparent power, S (VA) | √3 × V_LL × I_L | 3 × V_LN × I_L |
| Reactive power, Q (var) | √3 × V_LL × I_L × sin φ | 3 × V_LN × I_L × sin φ |
| Line current, I_L (A) | P ÷ (√3 × V_LL × PF) | P ÷ (3 × V_LN × PF) |
Real power does the work. Apparent power is what cables, transformers, and alternators must carry. Reactive power is exchanged between magnetic fields and the source without doing useful work, but it still occupies capacity.
Power factor ties the three together: PF = P ÷ S. A load with a PF of 0.80 needs 125 kVA of apparent power to deliver 100 kW. That 25 kVA gap is why a requirement stated only in kW is incomplete.
Generators are usually rated in kVA at a power factor of 0.8. A 250 kVA set is a 200 kW set at that convention. If your load runs at a different power factor, the kW and kVA limits no longer line up, and the alternator or the engine may reach its limit first.
Line-to-line versus line-to-neutral voltage
In a wye system, V_LL = √3 × V_LN. A 480 V line-to-line system has 277 V line-to-neutral. A 400 V system has 231 V. A 208 V system has 120 V.
These are the standard low-voltage systems listed in IEC 60038.
Use the voltage that matches the formula. Put 277 V into the √3 form and the result is 57.7% of the correct value, an understatement of 42%. Put 480 V into the 3 × V_LN form and the result is 173% of the correct value, an overstatement of 73%.
Both errors are common. Both survive a spreadsheet review because the formula still looks right.
A 30-second example
A 400 V, three-phase circuit carries 100 A per line at a power factor of 0.90.
- Apparent power: √3 × 400 × 100 ÷ 1,000 = 69.3 kVA
- Real power: 69.3 × 0.90 = 62.4 kW
- Reactive power: √(69.3² − 62.4²) = 30.2 kvar
At a power factor of 1.0, the same current would deliver 69.3 kW. The 10% difference is the cost of reactive power, and it appears on the generator, the cable, and the utility bill.
Working backwards: current from kW or kVA
To find current, rearrange the formula: I = kVA × 1,000 ÷ (√3 × V_LL). A 150 kVA load at 480 V draws 180 A. The same load at 400 V draws 217 A. Lower voltage means higher current for the same power, so you can’t copy conductor and breaker sizing between 400 V and 480 V projects.
What “Power Requirements” Means Beyond the Formula

A formula converts one number into another. A three-phase power calculation is a statement about a facility: how much power it needs, when it needs it, and how much of that demand arrives at the same time. Three different loads sit behind that statement.
| Load definition | What it counts | Typical use |
|---|---|---|
| Connected load | Every nameplate rating added together | Conductor and panel capacity, worst-case inventory |
| Demand load | Maximum simultaneous demand after demand factors | Utility service, transformer, generator running load |
| Design load | Demand load plus growth, starting, and site derating | Equipment specification and procurement |
The connected load is almost always the largest number. It’s also the least useful number for buying equipment, because no facility runs every load at nameplate at the same moment.
Demand factor and diversity factor
Demand factor is maximum demand divided by connected load. It’s always 1.0 or less. Diversity factor is the sum of individual maximum demands divided by the maximum demand of the whole system. It’s 1.0 or more.
Ten welders rated 20 kVA each have a connected load of 200 kVA. If no more than three run at once, the demand factor is 0.30 and the demand load is 60 kVA. A schedule that stops at 200 kVA would buy three times the required capacity.
Article 220 of NFPA 70, the National Electrical Code, sets demand factors for many load types and occupancies. For existing facilities, NEC 220.87 permits a measured approach: record the maximum demand over at least 30 days, then apply 125% of that value. That measured route is often more accurate than a calculated one, provided the recording includes seasonal heating and cooling.
Continuous versus noncontinuous loads
A continuous load runs for three hours or more. NEC 210.19 and 215.2 require conductors and overcurrent devices for continuous loads to be sized at 125% of the load. That 125% is a design factor, not a demand factor. It belongs in the circuit and feeder calculation, and it should be visible in the load schedule.
Why the utility bill is not the requirement
A utility demand reading is a useful cross-check. It isn’t a substitute for a load schedule. Billing demand may be ratcheted over a year, averaged over 15 or 30 minutes, based on kVA or kW, and adjusted by a power factor penalty. It also reflects the loads that existed during the billing period, not the equipment you plan to add.
Use the bill to validate the schedule. Use the schedule to state the requirement.
Three-Phase Power Calculation: Build a Load Schedule
A load schedule is a table, but the discipline is in the columns. Each row needs enough information to survive a review by an electrician, a supplier, and a finance manager.
Step 1: Inventory every load and its phase
List each load separately. Record its nameplate input, voltage, phase, power factor, efficiency, duty, and whether it’s continuous. Don’t combine a 30 kW motor and a 12 kW lighting circuit into a single “miscellaneous” row. That row will be the one nobody can defend.
| Column | Why it matters |
|---|---|
| Load ID and description | Traceability back to the equipment schedule |
| Quantity | Prevents a one-off load from being counted once |
| Nameplate kW, HP, or kVA | Starting point for the conversion |
| Voltage and phase | Determines which formula applies |
| Power factor and efficiency | Converts output kW to input kVA |
| Duty and demand factor | Converts connected load to demand |
| Phase allocation | Finds the loaded phase, not just the total |
Step 2: Convert each load to kVA
For a motor, convert shaft output to electrical input first: input kW = output kW ÷ efficiency. Then divide by power factor: kVA = input kW ÷ PF. A 30 kW motor at 93% efficiency and a PF of 0.86 draws 32.3 kW and 37.5 kVA.
If the nameplate gives full-load current, use kVA = √3 × V × I ÷ 1,000. That route already includes efficiency and power factor, so don’t adjust it twice.
Lighting and receptacles are usually rated in VA or watts. For a PF of 0.95, add 5% to the wattage to get VA. For electronic loads with a PF close to 1.0, the difference is small but not zero.
Step 3: Apply demand factors
Apply a demand factor to each row, not to the grand total. A compressor that runs at 100% and a welder that runs at 30% shouldn’t receive the same factor.
| Load type | Typical demand factor | Note |
|---|---|---|
| Motors in continuous process use | 0.9 to 1.0 | Check actual duty |
| HVAC | 0.8 to 1.0 | Depends on diversity and controls |
| Lighting | 1.0 | Usually all on at once |
| General receptacles | 0.3 to 0.5 | Office and shop differ widely |
| Welders | 0.3 to 0.6 | Depends on operator count and duty |
| Future expansion | 1.0 | Treat planned load as real load |
These are planning values. They aren’t a substitute for the code. Where a jurisdiction enforces NEC demand factors, use the code values and document the article you applied.
Step 4: Balance the single-phase loads
Three-phase loads distribute evenly by design. Single-phase line-to-line and line-to-neutral loads don’t. Allocate each one to a specific pair of lines or to a specific line and neutral, then total each phase separately.
This balancing example is an illustrative composite. An electrician wired every office receptacle and lighting circuit in a 208/120 V panel to L1. They did it because the first open breaker was there. The panel total looked fine. L1 carried 38% more current than L3, the neutral current was higher than expected, and the owner blamed the generator for voltage fluctuations. Moving two circuits to L2 and L3 fixed the problem without new equipment.
A practical target is to keep each phase within 10% of the average phase load. The voltages will still move under load, but the current imbalance stays within what a generator and a transformer can tolerate. NEMA MG 1 recommends keeping voltage unbalance at or below 1% for motors, and derating begins above that point.
Step 5: Check motor starting and voltage dip
The starting check is the part of a three-phase power calculation that most schedules miss. Add the greatest motor’s starting demand to the schedule before you finalize the requirement. A 30 kW compressor that draws 48 A at full load can draw 290 A for several seconds at direct-on-line start. That starting current is a requirement on the source even though it’s not a continuous load.
We’ll cover the check in its own section below. For now, add a column for starting method, starting current multiple, and resulting starting kVA.
Step 6: Add growth margin and state the requirement
Add a growth allowance of 15% to 25% to the demand load. The lower end suits a facility with a stable equipment list. The upper end suits a plant with a credible expansion plan or a history of adding loads between capital cycles.
This growth example is an illustrative composite. A plant engineer added a 15% allowance before a second shift was approved. Eighteen months later, the shift started without a second generator purchase. The allowance cost less than 4% of the project budget.
Then state the requirement in the form a supplier can quote:
- Total demand kVA
- Demand kW and overall power factor
- Voltage, frequency, and number of phases
- Maximum per-phase running current
- Largest motor, starting method, and starting kVA
- Duty: standby, prime, or continuous
Worked Example: A 480 V Fabrication Shop

The shop has a CNC machining center, a single-phase welding transformer, a screw compressor, lighting, rooftop HVAC, office loads, shop receptacles, and a 15% expansion allowance. All loads are 480 V three-phase unless noted.
| Load | Input rating | Connection | Demand factor | Demand kVA | L1 kVA | L2 kVA | L3 kVA |
|---|---|---|---|---|---|---|---|
| CNC machining center | 45 kW at PF 0.85 | 3-phase | 1.0 | 52.9 | 17.6 | 17.6 | 17.6 |
| Welding transformer | 30 kVA | L1-L2 | 0.6 | 18.0 | 9.0 | 9.0 | 0.0 |
| Screw compressor | 30 kW at PF 0.80 | 3-phase | 1.0 | 37.5 | 12.5 | 12.5 | 12.5 |
| Lighting | 12 kW at PF 0.95 | L1, L2, L3 | 1.0 | 12.6 | 4.2 | 4.2 | 4.2 |
| Rooftop HVAC | 60 kW at PF 0.85 | 3-phase | 0.9 | 63.5 | 21.2 | 21.2 | 21.2 |
| Office receptacles and IT | 15 kVA | Split evenly | 0.5 | 7.5 | 2.5 | 2.5 | 2.5 |
| Shop receptacles | 20 kVA | Split evenly | 0.3 | 6.0 | 2.0 | 2.0 | 2.0 |
| Future expansion | 15% of demand | 3-phase | 1.0 | 29.7 | 9.9 | 9.9 | 9.9 |
| Total | 227.7 | 78.9 | 78.9 | 69.9 |
The connected load is higher than 227.7 kVA because the table already applies demand factors. The demand load before growth is 198.0 kVA. The design load is 227.7 kVA.
At 480 V, a perfectly balanced 227.7 kVA load draws 274 A. The actual maximum is on L1 and L2: 78.9 kVA at 277 V line-to-neutral gives 285 A. The 4% difference is small but real, and it’s the number a supplier should see.
The demand kW is about 191 kW, with an overall power factor near 0.84. The stated requirement is therefore:
228 kVA, 191 kW at PF 0.84, 480 V, three-phase, 60 Hz, 285 A maximum per-phase running current, with a 30 kW direct-on-line compressor as the largest starting load.
That statement is complete enough to quote from. It isn’t yet a generator size. A 228 kVA running requirement doesn’t mean a 228 kVA generator, because the starting check and site conditions still have to be applied.
Want a second set of eyes on your schedule? Send us the load list and we’ll check the per-phase balance, starting duty, and stated requirement before you approach suppliers.
Power Factor: The Hidden Input in Three-Phase Power Calculation
Power factor is the ratio of real power to apparent power. It changes the kVA requirement without changing the kW requirement, which is why a load list that stops at kW is always incomplete.
How power factor changes kVA and current
For a fixed kW, kVA rises as power factor falls. Current rises in the same proportion.
| Power factor | kVA per 100 kW | Current multiplier versus PF 1.0 |
|---|---|---|
| 1.00 | 100 | 1.00 |
| 0.95 | 105 | 1.05 |
| 0.90 | 111 | 1.11 |
| 0.85 | 118 | 1.18 |
| 0.80 | 125 | 1.25 |
| 0.70 | 143 | 1.43 |
For example, a 100 kW load at PF 0.80 needs 125 kVA and 25% more current than the same load at PF 1.0. The cable, breaker, transformer, and generator all carry that difference.
Typical power factor by load type
| Load | Typical PF | Behavior |
|---|---|---|
| Induction motor at full load | 0.85 to 0.90 | Falls sharply at part load |
| Induction motor at light load | 0.50 to 0.70 | A major source of reactive demand |
| Resistance heating and incandescent lighting | 1.00 | No reactive component |
| LED and fluorescent lighting with drivers | 0.90 to 0.95 | Check driver datasheet |
| Welding transformer | 0.60 to 0.80 | Varies with weld duty |
| VFD | 0.95 and above | The drive corrects at its input |
Use measured values where available. If you have no meter, use the nameplate value for motors and a conservative 0.85 for a mixed industrial load. Document the assumption so the next reviewer can challenge it.
What correction changes, and what it doesn’t
Power factor correction capacitors reduce the reactive power drawn from the source. That lowers kVA and current upstream of the correction point. It doesn’t reduce kW, and it doesn’t reduce a motor’s starting current.
Correction has limits. Overcorrection at light load can create leading power factor, which some generators and controls handle poorly. Capacitors can also interact with harmonics from VFDs and rectifiers. Size correction from a measurement, not from a nameplate total.
For a quick conversion between kW, kVA, and current, use our kVA to kW conversion guide and the power factor calculator.
Motor Starting in Three-Phase Power Calculation

Running load is the steady state. Starting load is the event that decides whether the source holds voltage. A generator that carries 228 kVA of running load can still fail on a 30 kW motor. The starting demand is great, and the alternator may not accept the step.
Starting current multiples by starter type
| Starting method | Typical starting current | Typical starting kVA |
|---|---|---|
| Direct-on-line (DOL) | 6 to 8 times full-load current | 6 to 8 times running kVA |
| Star-delta | About 3 times full-load current | About one-third of DOL |
| Soft starter | 2 to 4 times full-load current | Reduced and adjustable |
| Variable frequency drive | 1.0 to 1.5 times full-load current | Close to running kVA |
The compressor in the worked example draws about 48 A at full load on 480 V. At six times full-load current, the starting current is 290 A and the starting kVA is 241 kVA. At seven times, it’s 338 A and 281 kVA. The starting event is the same order of magnitude as the entire running requirement.
How much voltage dip is acceptable
ISO 8528-5 describes generator transient performance in classes. The commonly quoted voltage dip limits on a load increase are 25% for G1, 20% for G2, and 15% for G3. G4 is set by agreement between manufacturer and customer.
Those limits describe the generator, not the load. Contactors may drop out at 15% to 20% dip. Variable-speed drives and controls may trip at a lower threshold. If the facility has sensitive loads, set a tighter target than the generator class allows.
Voltage unbalance is a separate limit. NEMA MG 1 recommends that motor supply voltage unbalance stay at or below 1%. Above that, motors must be derated, and at 5% unbalance the derating factor is about 75% of nameplate horsepower. A generator with a badly balanced single-phase load can create that condition even when its total kVA looks adequate.
Checking the starting kVA against the source
The starting check has three inputs: the motor’s locked-rotor current, the source’s ability to supply it, and the voltage dip the load can tolerate. The first is on the nameplate or in the motor data sheet. The second comes from the generator or transformer data. The third comes from the facility.
For a generator, the relevant data are the alternator’s transient reactance, the engine’s load acceptance, and the set’s specified ISO 8528-5 class. A supplier who quotes only a kVA rating hasn’t answered the starting question. Ask for the transient performance and the largest motor step the set can accept at the stated dip.
Our generator load calculation guide covers the starting calculation in more detail, including the voltage-dip formula and examples for DOL and reduced-voltage starts.
Turning the Requirement into an Equipment Rating
A requirement statement and an equipment rating aren’t the same document. The three-phase power calculation ends with a requirement, not a model number. The gap between them is made of duty class, site conditions, and accessory loads.
kVA, kW, and the 0.8 power factor convention
Generators are commonly rated in kVA at 0.8 power factor. A 250 kVA set is a 200 kW set at that convention. At PF 0.84, the same set may deliver more than 200 kW before the alternator reaches its kVA limit. However, the engine may reach its own limit first.
State both numbers in the quotation request. A supplier who quotes only kVA may deliver a set whose engine can’t carry the real load. A supplier who quotes only kW may deliver an alternator that can’t carry the apparent load.
Continuous, prime, and standby ratings
The same machine can carry different ratings depending on duty.
- Standby power is for utility outages and limited annual hours. It isn’t a continuous rating.
- Prime power is for continuous operation at variable load, with limited overload capability.
- Continuous power is for constant load over unlimited hours.
Match the rating to the duty, not to the price. A standby-rated set pressed into prime duty won’t deliver the hours the project assumes.
Temperature, altitude, and accessory loads
Generator ratings are stated at reference conditions. High ambient temperature, high altitude, and enclosure restrictions reduce the usable output. Accessory loads such as jacket water heaters, battery chargers, and cooling fans also draw power, and they’re easy to omit because they aren’t process loads.
Add them as rows in the schedule. A 2 kW jacket water heater and a 1 kW battery charger are small against 228 kVA. The principle still matters: if it draws power from the set, it belongs in the requirement.
When to move to generator sizing
Once the requirement is stated, the next step is a sizing check against a specific machine. That check adds the starting event, site derating, altitude, temperature, and duty rating. It’s a separate exercise from the load schedule, and it deserves its own document.
Our three-phase generator sizing guide walks through that step, including voltage configurations and unbalanced load rules. If you want a first-pass number before that conversation, the generator size calculator gives a starting range.
Eight Calculation Mistakes That Change the Answer

| Mistake | What it does | Fix |
|---|---|---|
| Mixing line-to-line and line-to-neutral voltage | Understates the result by 42% or overstates it by 73% | Use √3 with V_LL and 3 with V_LN |
| Multiplying the three-phase total by three again | Overstates the result by 200% | The √3 formula already totals all three phases |
| Treating connected load as demand load | Buys capacity no facility will use | Apply demand factors per row |
| Sizing on kW and ignoring power factor | Understates kVA and current | Convert kW to kVA at the actual PF |
| Balancing the total but not the phases | Hides a phase at 130% of average | Total L1, L2, and L3 separately |
| Forgetting single-phase line-to-line loads | Leaves two phases loaded and one idle | Allocate every line-to-line load explicitly |
| Skipping the largest motor’s starting check | Misses the event that decides the rating | Add starting kVA for the largest motor |
| Omitting growth and site derating | Produces a snapshot, not a requirement | Add 15% to 25% and apply site conditions |
Conclusion
A three-phase power calculation is complete only when it ends in a requirement a supplier can quote. That statement covers total kVA, kW at a stated power factor, voltage, frequency, maximum per-phase current, largest starting load, and duty. The √3 formula is the tool you use inside that discipline, not a substitute for it.
Start with the load schedule. Balance the phases before you total them. Check the largest motor before you accept a running-load number. Then size the equipment against the requirement, not against a nameplate total.
Ready to turn your load schedule into a specification? Contact ZC Power with your phase-by-phase list, voltage, frequency, and starting duty. Our engineering team will review the requirements and recommend a generator set rating from our 8 kVA to 4,000 kVA range.
Frequently Asked Questions
What is the formula for calculating three-phase power requirements?
For a balanced load, real power is P = √3 × V_LL × I_L × PF, and apparent power is S = √3 × V_LL × I_L. Use 3 × V_LN in place of √3 × V_LL when you have line-to-neutral voltage. A complete requirement also applies demand factors, checks per-phase balance, and adds motor starting and growth.
How do I calculate three-phase current from kW?
Convert kW to kVA first: kVA = kW ÷ PF. Then use I = kVA × 1,000 ÷ (√3 × V_LL). A 100 kW load at PF 0.85 is 117.6 kVA. At 480 V, the line current is 141 A.
What is the difference between connected load and demand load?
Connected load is the sum of every nameplate rating. Demand load is the maximum simultaneous load after demand factors. A facility can have 400 kVA connected and 180 kVA demand. Equipment is specified from the demand load plus growth and starting allowances, not from the connected total.
How do I balance single-phase loads on a three-phase panel?
Assign each single-phase load to a specific line or line pair, then total L1, L2, and L3 separately. Move circuits until each phase is within 10% of the average. Recheck the neutral current and the voltage unbalance after the move.
How much margin should I add to a three-phase power requirement?
Add 15% to 25% to the demand load. Use 15% for a stable equipment list and 25% for a facility with a credible expansion plan. Keep the growth allowance as a separate row so the reader can see it and challenge it.
Can a 400 V generator run a 480 V system?
No, not directly. A 400 V generator can’t supply a 480 V load at its rated voltage. The voltage, frequency, and phase configuration must match the facility, or a transformer must be added.
What power factor should I use if I don’t have a meter?
Use the motor nameplate value for motors and 0.85 for a mixed industrial load. For an existing facility, a power meter reading over a normal production week is better than any assumption. Document the value you used, because it changes the three-phase power calculation and the current by the same proportion.